Mandatory Pre-Bid Meetings - Do I really have to attend?

There is an emerging trend in public bids to include a requirement for a mandatory pre-bid meeting. The requirement to attend the pre-bid meeting is typically set forth in the Instructions to Bidders ("ITB") and provides that a contractor’s failure to attend will result in its bid being rejected as non-responsive.  

As a preliminary matter, there is no Mississippi statute or regulation which requires a public agency to conduct a pre-bid meeting or for a contractor to attend a pre-bid meeting to qualify it to submit a bid.  This is a "requirement" typically included in the Instructions to Bidders by the Owner/Architect.  One reason it may be included is to give "local" contractors an advantage over "foreign" contractors. "Foreign" contractors are forced to expend additional time and effort to attend the pre-bid meeting, and cannot simply throw a bid together and submit it to the public agency. Another reason the requirement is included may be to give the opportunity for the Owner/Architect to give final, pre-bid information on the project requirements and, sometimes, even to serve as an alternative (though not a good one) to an amendment to the ITB.

A contractor that does not attend the pre-bid meeting risks the potential for having its bid rejected as non-responsive.  If the Owner/Architect truly intends to enforce this requirement, at bid opening the Owner/Architect should examine each bid to determine the identity of the bidder and compare it to the list of attendees at the pre-bid meeting.  If the bidder did not attend the pre-bid meeting, the Owner/Architect should return the bid unopened.

In most instances, the Owner/Architect will open the bids and address the issue only if the apparent low bidder has not attended the pre-bid meeting.  The bigger the spread between the apparent low bidder and the second low bidder, the more likely it is that failure to attend the mandatory pre-bid meeting will be waived. The Mississippi Attorney General has opined that "a bidding irregularity may be waived if: (1) the irregularity does not destroy the competitive character of the bid by affecting the amount of the bid thereby giving the bidder an advantage or benefit over other bidders and (2) the irregularity does not involve noncompliance with a statutory or regulatory requirement."  Because the requirement to attend a pre-bid meeting is not a statutory or regulatory requirement, Owners/Architects frequently waive the pre-bid meeting requirement without a challenge.  

If, however, the Owner/Architect does not agree to voluntarily waive the irregularity, an argument can be made that by opening the contractor’s bid that did not attend the pre-bid meeting; the Owner/Architect has already waived the requirement.   

There is another alternative. A contractor that is concerned about the requirement for a mandatory pre-bid meeting can file a pre-bid protest with the public agency challenging this requirement as unduly restrictive on competition and not in the best interests of the public.   

Checklist for Mississippi Construction Contractors

If you have ever been the apparent low bidder on a public construction project and had your bid rejected because of an irregularity in the bid documents, you are not alone.  What is even more frustrating, and will make you fighting mad, is when the public agency decides to waive the same irregularity of a competitor when you are the second low bidder.  Perhaps the best way to avoid this situation is to make sure that you have completed your bid in strict accordance with the instructions to bidders.  I know it is difficult to focus on all the particulars when less than an hour before the bid is to be submitted subcontractors and suppliers are sending in prices or changing the ones previously provided.  Here is a simple bid checklist that may help you avoid those last minute mistakes.

  • Read the "Instruction to Bidders" when you obtain a copy of the solicitation to make sure that there are no unusual or different bid requirements. 
    • Pre-Bid Conference
    • Bid Bond
    • Site Visit
    • Listing of Subcontractors
  • Prepare the bid envelope in advance, identifying (1) the project, (2) the person to whom the bid is to be submitted, (3) the location where the bid is to be submitted and (4) the date and time for the submission of the bid.  ALWAYS PLACE CERTIFICATE OF RESPONSIBILITY NUMBER ON THE OUTSIDE OF THE ENVELOPE.
  • Complete the bid form and check to determine whether all the blank spaces for prices are completed with a dollar amount or a "---" or "-0-".
  • Check your addition and multiplication for unit prices and total bid price.
  • Acknowledge all Amendments/Addenda to the solicitation.
  • List subcontractors, if required.
  • Sign and date the bid documents.
  • Check the bid bond, if required, to make sure that it is in the correct amount and proper form.
  • Place bid documents and bid bond, if required, into envelope and submit.

In the event you are determined to be the apparent low bidder, and your bid is not more than ten percent (10%) above the amount of funds allocated for the project, it is likely that you will be awarded the contract.