Agreement to Arbitration Trumps Right to Jury Trial

In a recent Mississippi Supreme Court decision the Court considered language in a contract which contained an arbitration provision, which excluded aesthetic-effect claims from arbitration. Click here to see decision. The contract in question was the AIA Document A101-1997 Standard Form of Agreement Between Owner and Contractor and AIA Document A201-1997 General Conditions for the Contract for Construction. The Owner maintained that because the contract stated "[a]ny Claim arising out of or related to the Contract, except Claims relating to aesthetic effect and except those waived…shall, be subject to mediation as a condition precedent to arbitration or the institution of legal or equitable proceedings by either party" there had been no clear waiver of its right to a jury trial. The trial court disagreed and on appeal the Mississippi Supreme Court affirmed.

The Court found the language of the contract required arbitration of all claims with the exception of those relating to aesthetic effect. Opinion on whether there had to be an express waiver of the right to a jury trial, the Court stated:

No caselaw suggests that, to be valid, an arbitration agreement must include an express statement which waives the right to a jury trial.

[T]he Constitution does not ‘confer the right to a trial, but only the right to have a jury hear the case once it is determined that the litigation should proceed before a court. If the claims are properly before an arbitral forum pursuant to an arbitration agreement, the jury trial right vanishes.

McKenzie Check Advance of Miss., LLC v. Hardy, 866 So.2d 446, 455 (¶30)(Miss. 2004)(citations omitted). Section 11-15-103 requires only a written agreement to arbitration.

Thus, the Court makes it clear that where a contract includes an agreement to arbitrate disputes, there is no need to have an express waiver of the right to a jury trial.

Failure of Prime Contractor to Comply With "Percentage of Work" Requirements Entitles Government to Damages

In a case of first impression, the United States Civilian Board of Contract Appeals upheld a contracting officer’s final decision assessing damages against a prime contractor that failed to comply with the requirement to perform at least 50% of the on-site work. On a contract awarded by the Federal Highway Administration ("FHWA"), prime contractor, Singleton Enterprises ("Singleton") subcontracted the vast majority of its work to Talley Construction ("Talley"). Singleton’s only employees on-site were supervisors, which Singleton apparently borrowed from Talley but paid directly. It was unclear whether Singleton had paid for equipment used on the site, but the CBCA determined that whether or not Singleton had paid for equipment costs, it still performed substantially less than 50% of the value of on-site work.

The FHWA decided that if Singleton did not perform the on-site work, it was not entitled to the benefit of the unit prices it charged for that work. Talley was essentially acting as prime contractor so the FHWA decided it should only pay Singleton what Singleton was paying Talley. To calculate its damages, once the final quantities were determined, the FHWA multiplied Talley’s unit price to Singleton for the work, which was less than Singleton’s unit price to the FHWA for the work. Singleton had already been paid more than the FHWA would have paid based on Talley’s pricing. The appeal upheld not only the FHWA’s decision that it was entitled to recoup its "overpayment" damages from Singleton for not meeting the percentage of work requirement but also the reasonableness of the FHWA’s method of calculating its damages for that breach.

The decision notes that it has no precedential value. However, in similar circumstances, contractors should expect both the Department of Transportation and the Civilian Board of Contract Appeals to act as they did here. See Singleton Enterprises v. Department of Transportation, CBCA No. 2716, June 14, 2012.

Mississippi Code Section 31-5-41 Not Applicable to Performance Bonds

The Mississippi Supreme Court recently decided an appeal concerning whether Miss. Code Ann. § 31-5-41 applied to a performance bond surety where the performance bond incorporates the terms and conditions of a construction contract. Miss. Code Ann. § 31-5-41 provides that all public or private construction contacts that contain a provision agreeing to "indemnify or hold harmless another person from that person’s own negligence is void as against public policy and wholly unenforceable." It also states that "[t]his section does not apply to construction bonds or insurance contracts or agreements."

In the case decided by the Court, the general contractor was sued by the owner of a building for alleged construction defects. The owner also sued the performance bond surety for breach of the performance bond and bad faith denial of its claims. The surety sought to enforce its indemnity agreement with the general contractor. However, the trial court denied the surety’s claim for indemnification finding its potential liability arouse out of its own negligence. The Mississippi Supreme Court reversed the trial court simply finding the language of Miss. Code Ann. § 31-5-41 provides that it does not apply to "contraction bonds or insurance contracts or agreements." The Court went on to state that "[t]his remains true even if the performance bond incorporates the construction contract by reference."

Even though the general contractor was unable to use Miss. Code Ann. § 31-5-41 as a defense against the surety’s claim for indemnity, this statutory provision does afford the general contractor protection against broad indemnity provisions in other construction related contracts.

When do you have a contract with a public entity?

It can be unclear when a contractor bidding on a public construction project actually has a binding contract with a public entity. This question appears to have been addressed by the Mississippi district court in Northeast Mississippi Community College District v. Vanderheyden Construction Company. In that case, the community college had issued an advertisement for bids from qualified contractors for the construction of a new science and math building. The advertisement reserved the right to reject any and all bids. After bids were opened, Vanderheyden was declared the low bid. The Board of Trustees ("the Board") voted to award the contract to Vanderheyden but after the board meeting the second low bidder challenged the award alleging a number of deficiencies in Vanderheyden’s bid. Rather than risk a lawsuit by the second low bidder, the Board decided to rescind the award and readvertise. At the second bid opening the protester on the original procurement was the low bidder and Vanderheyden was the second low bidder.

The issue presented to the district court was whether the Board could properly rescind its prior award to Vanderheyden and readvertise the project. The district court concluded that "a public entity cannot reject all bids and readvertise the project after it has already accepted the lowest responsible bidder." In analyzing the actions of the Board, the district court when on to state:

[T]he court is of the opinion that once the board chose to accept Vanderheyden’s bid, the reserved right to reject any and all bids had not been exercised and it was no longer operative. To hold otherwise would be contrary to well-established principles of contract law and would permit the possibility of favoritism in public bidding, the very evil which the bidding process statutes were enacted to prevent.

Therefore, once a public entity has officially accepted a bid, there is a binding contract between the parties unless the public entity has expressly conditioned the award upon certain requirements.

Appeals from School Board Orders--Do not delay!

If you are bidding on a project for a school board and are aggrieved by the decision to award the contract to another party, you must appeal the order "within ten (10) days from the date of adjournment of the meeting at which the order is entered."  Miss. Code Ann. § 37-7-115. The procedure for appealing the award decision is the same as set forth in Miss. Code Ann. § 11-51-75 and requires preparing and filing a bill of exceptions with the circuit court.  Because of the short time within which to appeal the decision, a contractor must not delay in deciding whether to appeal or walk away and fight another day.

General Disclaimers in Plans and Specifications

In an attempt to avoid liability for the various deficiencies in its plans and specifications, some architects and engineers rely upon the general disclaimers set forth in the contract documents. However, the United States Supreme Court has held these general disclaimers are unenforceable as a matter of law. In U.S. v. Spearin, the Supreme Court ruled that the Owner is responsible and affirmatively warrants the adequacy of its plans and specifications and that responsibility "is not overcome by the usual clauses requiring builders to visit the site, check the plans, and to inform themselves of the requirements of the work." Similarly, in Baldi Bros. Constructors v. U.S., the U.S. Court of Federal Claims ruled that such general contractual provisions, even including a provision which states the owner does not guarantee the statements of fact in the specifications, will not relieve the owner from liability for providing misleading information to the contractor

Neither the Owner nor the design professional can fully shield itself from liability for its errors and/or omissions in the plans and specifications through disclaimers in the contract documents. Likewise, disclaimers shifting the burden of costs associated with errors and/or omissions are also generally unenforceable. A contractor is therefore typically entitled to rely on the representations in the plans and specifications, but the contractor should nevertheless perform a reasonable site inspection and review of the plans and specifications so that obvious errors and/or omissions can be addressed prior to bidding.

When a contractor does find itself confronted with such general disclaimers and the owner and/or architect nonetheless issues a directive to proceed, the contractor must document its position with regard to the error and/or omission to protect its position. The lack of such documentation may substantially impair, if not be fatal, to the contractor’s claim for additional compensation and/or time.

July 1, 2011 Deadline for ALL Employers to Comply with Mississippi Employment Protection Act

By now, most employers have heard of the federal "E-Verify" program which is designed to identify and prohibit employment of illegal aliens. In the 2008 legislative session, the Mississippi Legislature adopted the "Mississippi Employment Protection Act" ("MEPA") which has features similar to the "E-Verify" Act, but is broader in its application.

Unlike federal law, the MEPA applies to every employer. An "employer" is defined as "any person or business that is required by federal or state law to issue a United States Internal Revenue Service Form W-2 or Form 1099 to report income paid to employed or contracted personnel in Mississippi." In other words, the MEPA applies to virtually everyone.

So what must the employer do under the MEPA? "Every employer shall register and utilize the status verification system [i.e., the federal E-Verify Program] to verify the federal employment authorization status of all newly hired employees." There are no exceptions! So if you are a small business and hire just one new employee, you are still covered and expected to verify the employment authorization status of the employee. Under the law, employers in the state of Mississippi shall only hire U.S. legal citizens or legal aliens. The E-Verify Program is the authorized means by which employers can verify the employee’s status.

The MEPA was implemented in stages since its adoption. However, effective July 1, 2011, the MEPA is fully implemented and, as mentioned previously, applies to all employers.

What are the consequences for failing to comply? Substantial! Any contract with the state or other public body can be cancelled and you can be ineligible for any public contracts for up to three years. You can also lose any license, permit, certificate or other document issued by any public entity which gives you the right to do business in Mississippi for up to one year. Effectively, these consequences could put you out of business, even if you do not hire an illegal alien! The mere failure to follow the verification requirements could subject you to these penalties.

Can the state do this? Yes. On May 26, 2011, the United States Supreme Court handed down a decision affirming similar laws in Arizona. In the case of Chamber of Commerce of the U.S.A. v. Whiting, the U.S. Supreme Court upheld Arizona’s law which the Court concluded did not preempt the federal law, but instead merely imposed licensing conditions on businesses operating within the state. The Supreme Court further concluded that nothing prevented states from making mandatory the federal E-Verify program. The MEPA appears to be consistent with the U.S. Supreme Court’s ruling and, therefore, would likely be upheld.

Bottom line: Comply with the MEPA. If you have not already registered for E-Verify, do so now and learn how to use it so that you will be ready on July 1st.

Bid Protests--Time is not on your side

If you believe you have grounds for protesting the decision of a board of supervisors, or municipal authorities of a city, town, or village to reject a bid or award a contract, you need to act promptly. The clock is ticking and fast.

Under Miss. Code Ann. §11-51-75 (Rev. 2002) you have only ten (10) days from the adjournment of the meeting to appeal the adverse decision of the board of supervisors or municipal authorities to the circuit court. Do not wait for the official copy of the minutes to the meeting. Contact your legal counsel immediately since he/she will need to prepare a bill of exceptions (essentially a statement of the facts) that must be signed by the president of the board of supervisors or the municipal authority and presented to the circuit court clerk to perfect the appeal.

Remember, in the context of bid protests, if you delay you will lose the right to challenge the decision of the board of supervisors or municipal authority.

Choose Your Arbitration Clause Wisely

During the last several decades arbitration has become a valuable method for resolving disputes between parties in the construction setting. A simple arbitration provision might read as follows:

Claims and disputes not resolved shall be decided by arbitration which shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect.  The locale of any arbitration shall be Jackson, Mississippi.

Simple and straightforward, but is it enough? It depends on what your expectations are for arbitration. An arbitrator is bound by the requirements of the arbitration clause. Therefore, if you are drafting an arbitration clause, you might want to consider including certain "bells and whistles" that will get you to the finish line faster. Here are some items you might want to consider including in an arbitration clause. 

  • Location of the arbitration proceeding;
  • Number of arbitrators and experience requirements;
  • Limitations on discovery;
  • Specific rules governing admissibility of evidence at hearing, i.e. state or federal rules of evidence verses the liberal rules for admissibility of the AAA;
  • Time within which arbitration hearing must be conducted; and
  • Payment of fees and costs.

Remember, it is your arbitration clause so draft it to suit your business objectives.

Arbitration Again - Is saying it once enough with multiple documents?

The Mississippi Court of Appeals just released yet another decision in its recent review of arbitration provisions. This time the case dealt with multiple documents, one of which did not include an arbitration provision.

The case involved a couple who had borrowed money from a bank. As is typical with loan transactions, numerous documents were signed as a part of the transaction. The loan-related documents contained an arbitration provision which included in part that "any controversy concerning whether an issue is arbitrable shall be determined by the arbitrator". However, the deed of trust contained no arbitration provision.

The borrowers contended that their house and three acres were not included in the property that had been pledged under the deed of trust for the loan; the bank disagreed. The borrowers filed suit and the bank demanded arbitration. The borrowers claimed the deed of trust was not subject to arbitration.

On appeal, the Mississippi Court of Appeals ruled that the arbitration provisions in the loan documents "should be considered incorporated into the deed of trust" because "separate agreements executed contemporaneously by the same parties, for the same purposes, and as part of the same transaction, are to be construed together." Accordingly, the Mississippi Court of Appeals overturned the trial court and ordered arbitration of the matter.

The lesson of the decision is that some statements bear repeating. In this case, the Court concluded that the parties had agreed to arbitration, even though the deed of trust did not specifically so state. However, the result may not be the same in other situations. Although it may seem repetitious, the safest course of action is to include an arbitration provision in every document related to a transaction. Otherwise, you may find yourself fighting to enforce the agreement to arbitrate as the bank did in this case.

When is Enough, Enough - The "Shaken Faith Doctrine"

 

Contractors are occasionally confronted with a subcontractor that just cannot seem to get the job accomplished in a timely or satisfactory manner. Despite repeated warnings, the subcontractor’s performance may not improve. Because termination is an extreme remedy, contractors are generally hesitant to terminate a subcontractor. But when is enough, enough? The Court of Appeals for Mississippi provided some guidance on this issue in Byrd Brothers, LLC v. Herring, 861 So.2d 1070 (Miss. Ct. App. 2003).

In Byrd, the contractor retained a subcontractor to perform plumbing work on a condominium complex. Shortly after the plumbing work commenced there was a dispute concerning the scope of work to be performed by the plumbing subcontractor. There were also issues with the quality of the work performed by the plumbing subcontractor. The contractor repeatedly requested the plumbing subcontractor remedy the deficiencies. However, the plumbing subcontractor failed to adequately address the concerns complaining the contractor was "being too picky". When the contractor discovered billing irregularities, the plumbing subcontractor was asked to leave the project site. The contractor later requested the plumbing subcontractor meet to discuss his performance issues and completion of the project but the plumbing subcontractor refused unless the contractor immediately paid him some money. When this did not occur, the plumbing subcontractor refused to meet and did not to return to the project. The contractor retained another plumbing subcontractor to complete the work.

The original plumbing subcontractor sued the contractor for the subcontract balance and the contractor asserted a counterclaim against the plumbing subcontractor for the cost to complete the plumbing work. The trial court found in favor of the subcontractor. In reversing the trial court judgment and ordering a new trial, the Mississippi Court of Appeals articulated the following legal principle:

A party who has breached or failed to properly perform a contract has a responsibility and a right to cure the breach. The non-breaching party must give him a reasonable opportunity to cure the breach. However, the right to cure is not unlimited.

Where the breach is a material one, the non-breaching party has a right to end the contract, but in doing so he is also obligated to minimize his damages. Likewise, when the conduct of the breaching party has been of such a nature as to cause a loss of confidence or "shaken faith," the offended party is entitled to end the contract, but he remains responsible for mitigating damages.

 

(Citations omitted.)

The Byrd decision highlights the importance of providing a breaching party the opportunity to cure its breach. One warning may not be enough. Contractors need to be vigilant in their efforts to document incomplete and deficient performance and afford adequate opportunities for the subcontractor to "do the right thing". If the subcontractor fails to timely and satisfactorily respond to the contractor’s demands to cure the incomplete and/or deficient work, the cumulative impact of the incomplete and/or deficient work and the lack of responsiveness on the part of the subcontractor may result in a lack of confidence, i.e. "shaken faith", sufficient to entitle the contractor to complete the work and mitigate its damages.

Mississippi Bureau of Building, Grounds and Real Property Management's New Standards for Disqualification of Bidder

If you are bidding on projects awarded through the Mississippi Department of Finance and Administration, Bureau of Building, Grounds and Real Property Management ("the Bureau"), you might not be awarded the contract, even if you are the apparent low bidder.

The Bureau is very particular about with whom it does business. Effective May 18, 2009, the Bureau has expanded the grounds for disqualifying a bidder from competition. (Link to rules.) These recent changes are highlighted below.

1.04 DISQUALIFICATION OF BIDDER: A Bidder may be disqualified for any of the following reasons:

A.  Failure to comply with the bid requirements.  (This provision was in 600.53 but missing in 1.04 of the Instructions to Bidders.

B.  Bidder is in arrears on existing Contract with the Bureau or another state agency.

C.  Bidder is, or anticipates being, in litigation or arbitration with the Bureau or another state agency.

D.  Bidder has defaulted on a previous Contract.

     

    BOB Manual, Instructions to Bidders, Section 00100, Part 1, General, Paragraph 1.04.

Mississippi’s Public Procurement Statute requires award to the "lowest and best bidder". However, the Mississippi Courts have recognized that the lowest bid may not necessarily be the best bid. Thus, state agencies have been afforded considerable deference when deciding which contractor has submitted the "lowest and best bid". One of the areas the Mississippi Supreme Court has recognized may be considered in the evaluation of bids is a contractor’s past performance record. However, in my opinion, the Bureau’s grounds for disqualification impermissibly expand the area of inquiry by seeking to penalize a contractor for exercising its contractual right to pursue a claim against the Bureau or another state agency with which the contractor has a contract.

The Bureau’s new grounds for disqualification gives it the authority to now reject a bid if the contractor "anticipates" being in litigation or arbitration. Hypothetically, this means that if a contractor has a contract with the Bureau or another state agency, writes a "claim" letter stating the contractor believes it has a right to an equitable adjustment in the contract price and/or time and subsequently submits a bid on another Bureau project, the contractor’s bid may be rejected because the letter could be construed as a sign the contractor "anticipates" being in litigation or arbitration with the Bureau. The Bureau may even require a certification as part of its bid requirements wherein the contractor must represent it does not anticipate being in litigation or arbitration with the Bureau or another state agency. The obvious intent of this provision is to discourage contractors from asserting claims against the Bureau or another state agency on construction projects. It appears the Bureau has made the decision that such draconian tactics are more effective then dealing with legitimate claims which the contractor has a right to assert under the Bureau’s contract documents.

Checklist for Mississippi Construction Contractors

If you have ever been the apparent low bidder on a public construction project and had your bid rejected because of an irregularity in the bid documents, you are not alone.  What is even more frustrating, and will make you fighting mad, is when the public agency decides to waive the same irregularity of a competitor when you are the second low bidder.  Perhaps the best way to avoid this situation is to make sure that you have completed your bid in strict accordance with the instructions to bidders.  I know it is difficult to focus on all the particulars when less than an hour before the bid is to be submitted subcontractors and suppliers are sending in prices or changing the ones previously provided.  Here is a simple bid checklist that may help you avoid those last minute mistakes.

  • Read the "Instruction to Bidders" when you obtain a copy of the solicitation to make sure that there are no unusual or different bid requirements. 
    • Pre-Bid Conference
    • Bid Bond
    • Site Visit
    • Listing of Subcontractors
  • Prepare the bid envelope in advance, identifying (1) the project, (2) the person to whom the bid is to be submitted, (3) the location where the bid is to be submitted and (4) the date and time for the submission of the bid.  ALWAYS PLACE CERTIFICATE OF RESPONSIBILITY NUMBER ON THE OUTSIDE OF THE ENVELOPE.
  • Complete the bid form and check to determine whether all the blank spaces for prices are completed with a dollar amount or a "---" or "-0-".
  • Check your addition and multiplication for unit prices and total bid price.
  • Acknowledge all Amendments/Addenda to the solicitation.
  • List subcontractors, if required.
  • Sign and date the bid documents.
  • Check the bid bond, if required, to make sure that it is in the correct amount and proper form.
  • Place bid documents and bid bond, if required, into envelope and submit.

In the event you are determined to be the apparent low bidder, and your bid is not more than ten percent (10%) above the amount of funds allocated for the project, it is likely that you will be awarded the contract.

Show Me The Money...Now!

In these difficult economic times, an Owner and/or Contractor may be tempted not to make full and final payment after the work is complete and there is beneficial use and occupancy of the facility. The Owner and/or Contractor may justify this conduct even though there is not currently a problem with the work because there "may" be unanticipated future problems with that will need to be addressed. However, withholding payment for potential defects or warranty issues could turn out not to be a wise decision.

An Owner and/or Contractor’s "belief" that it may have warranty claims sometime in the future may be insufficient to justify withholding of final payment as explained by the Mississippi Supreme Court in Crawford Commercial Constructors, Inc. v. Marine Industrial Residential Insulation, Inc., 437 So.2d 15 (Miss. 1983). In that case, a subcontractor sued the general contractor for payment under a roofing contract. The general contractor had refused to pay the subcontractor on the basis that it "believed the roof was improperly installed, so that [the general contractor] will ultimately be required to repair it to satisfy the building’s owner." Id. The Court ruled that the general contractor’s "beliefs" were conjectural. Id. at 16. In affirming the trial court’s decision in favor of the subcontractor, the Mississippi Supreme Court stated:

Under our authorities there must be a present, existent actionable title or interest which must be completed at the time the cause of action is filed. (citations omitted). A mere inchoate right is not sufficient and neither is a prospective danger of injury. (citations omitted)…"It is certainly an undisputable and invariable rule of law that a right of action must be complete when an action therefore is commenced…."…"we consider it to be the well-settled, general rule, that the facts which constitute the ground of a suit must exist at the time the suit is instituted…"

 

Id. at 16.

In addition to this jurisprudence, Mississippi has enacted what are generally known as "Prompt Payment Statutes" for both public and private construction contracts. Both of these statutes require timely final payment once the contract has been determined to be substantially complete or there has been beneficial use and occupancy. There are also "Late Payment Interest Statutes" which apply when a contractor fails to make payment "without reasonable cause" to its lower tier subcontractors or suppliers within fifteen (15) days after receipt of payment.

There is no provision for recovery of attorneys’ fees in either the "Prompt Payment Statutes" or the "Late Payment Interest Statutes." Contractors therefore need to ensure the issue of attorneys’ fees associated with collection efforts are adequately addressed in their contract documents.

You can expect this case law and these statutes to be cited frequently in payment disputes during these difficult economic times.

Bureau of Building, Grounds and Real Property Management Updating Construction Manual

The Mississippi Department of Finance and Administration, Bureau of Building, Grounds and Real Property Management is currently updating its BOB Construction Manual.  This is your opportunity to participate in the process.  If you want to be heard, you should email Glenn Kornbrek, the Assistant Director for the Bureau of Building, Grounds and Real Property Management (KornbrG@dfa.state.ms.us).  Mr. Kornbrek’s telephone number is (601) 359-3894.

Forum Selection Clauses

The Mississippi  courts will enforce forum selection clauses when the intent is clear and unequivocal.  When confronted with challenges to the enforcability of a forum selection clause, the  first step in analysis is whether it is mandatory or permissive. Titan Indemnity Company v. Hood, 895 So.2d 138, 146-47 (Miss. 2005) (.pdf). The determination of what language is considered mandatory as opposed to permissive was carefully examined and discussed in Bently v. Mutual Benefits Corp., 237 F.Supp.2d 699 (S.D. Miss. 2002) (.pdf). In Bently, the district court was tasked with determining whether to enforce a forum selection clause with language strikingly similar to the language found in SCP’s terms and conditions. Its analysis followed the two-step inquiry articulated by the Fifth Circuit in Caldas & Sons, Inc. v. Willingham, 17 F.3d 123 (5th Cir. 1994) (.pdf). As to whether the forum selection clause was mandatory or permissive, the district court reasoned that "a mandatory forum selection clause has express language limiting the action to the courts of a specific locale which is clear, unequivocal and mandatory." Bently, 237 F.Supp.2d at 702 (emphasis added). The district court when on to cite a number of decisions discussing the importance of limiting language in the forum selection clause to obviate any uncertainty with regard to the exclusivity of the chosen forum.

If the forum selection clause is considered mandatory, the second step in the legal analysis requires the court to consider (1) whether "Its incorporation into the contract was the result of fraud, undue influence or overweening bargaining power; (2) [t]he selected forum is so gravely difficult and inconvenient that the resisting party will for all practical purposes be deprived of its day in court; or (3) [t]he enforcement of the clause would contravene a strong public policy of the forum in which the suit is brought, declared by statute or judicial decisions." Titan Indemnity Company v. Hood, 895 So.2d 138,146-47 (Miss. 2005).