Do you have coverage under your Commercial General Liability Policy for Defective Subcontractor Construction?

Less than one week after placing readers on alert about the pending decision of Architex Association, Inc. v. Scottsdale Insurance Company, the Mississippi Supreme Court has issued its decision in that case addressing the following narrow issue with regard to a Commercial General Liability ("CGL") policy:

Whether the intentional act of hiring subcontractors by an insured general contractor precludes the possibility of coverage?

The Court found "that under Scottsdale’s CGL policy, the term ‘occurrence’ cannot be construed in such a manner as to preclude coverage for unexpected or unintended ‘property damage’ resulting from negligent acts or conduct of a subcontractor unless, otherwise excluded or the insured breaches its duties after loss." Slip Op. at page 27. Thus, "[f]aulty workmanship, defective work, et al., may be accidental, intentional, or neither." Slip Op. at page 23.

The United States Court of Appeals for the Fifth Circuit in ACS Construction Company v. CGU, 332 F.3d 885 (5th Cir. 2003) had previously concluded that since hiring a subcontractor is a deliberate and intentional decision by a general contractor, any subsequent act by the subcontractor must be intentional and not covered under the definition of an "occurrence". The insurance industry has used ACS to deny coverage for defective work by subcontractors, even though many general contractors purchased policies and paid premiums with the understanding that their CGL policy would provide coverage.

The Mississippi Supreme Court’s decision in Architex brings clarity to the issue stating that "[w]hile the alleged ‘property damage’ may have been ‘set in motion’ by Architex’s [the general contractor] hiring of the subcontractor, the ‘chain of events’ may not have ‘followed a course consciously devised and controlled by [Architex], without the unexpected intervention of any third person or extrinsic force.’" In other words, hiring a subcontractor will not preclude coverage under a CGL policy.

Even if the insurer does not unequivocally agree that there is coverage under the CGL policy, the insurer may agree to defend the general contractor under reservation of rights. This means the insurer will pay the general contractor for the cost associated with defending the claim of defective workmanship. This does not mean the insurer gets to select the attorney to defend the claim, it means the insurer must pay for the attorney the general contractor selects to defend the claim. Therefore, it would be wise for the general contractor to select a construction lawyer to defend the claim rather than the insurer’s preferred attorney who is likely to have experience in defending slip and fall cases and car wrecks and not complex construction defect cases.

The Architex decision is good news for general contractors. However, the decision also admonishes general contractors that there are other reasons for denial of coverage such as failure to give timely notice of a potential claim. Slip Op. at page 12, fn. 11. This means that general contractors should place their insurance carrier/agent on written notice of any potential claim for which the CGL policy might arguably provide coverage. Otherwise, coverage may ultimately be denied.

CAN I RELY ON MY SUBCONTRACTOR'S CERTIFICATE OF INSURANCE?

Every contractor generally requires proof of insurance from its subcontractors, especially with respect to worker’s compensation insurance. In satisfaction of this contractual requirement, subcontractors commonly provide a certificate of insurance to the prime contractor. Is the certificate of insurance sufficient? It may not be.

Many certificates of insurance contain a disclaimer that the certificate is for informational purposes only and does not extend the policy. The disclaimer is a warning that you must look at the policy itself for specific coverage.

In Complete Roofing Services, et al. v. Doherty Duggan & Rouse Insurors, 5th Circuit Court of Appeals (5th Cir. 2009), a certificate of insurance was issued to a general contractor, but the worker’s compensation coverage denoted in the certificate was limited to occurrences only in Georgia. The subcontractor’s employee was injured in Mississippi. The court determined that the "Georgia only" policy did not provide coverage for the injured employee. As a result, the general contractor’s worker’s compensation was required to cover the claim. In this case, it was a catastrophic claim costing the worker’s compensation carrier over $1,000,000.

The best business "policy" is to always obtain and read the actual insurance policy itself. In reviewing the policy, take into consideration the circumstances related to each particular project. For example, consider the following factors: Is the subcontractor from another state? If so, are the subcontractor’s employees from another state or local? Is the subcontractor’s insurance policy state specific? If so, does it cover the state where the project is located? Will any leased employees be used for the project? If so, does the insurance policy cover leased employees or is other insurance required? Are there any warnings or disclaimers in the policy? If so, take heed and consider whether other additional insurance is necessary.

Although the Complete Roofing Services case dealt with a contractor/subcontractor relationship, these basic rules apply to any situation where one party contractually requires insurance from another party. The bottom line is this: get the full policy and read it. This applies to your own insurance policy as well!

(D. Drew Malone is a member of Robinson, Biggs, Ingram, Solop & Farris, PLLC who practices in the area of insurance defense. Drew personally handled this case and contributed to drafting this blog.)

No Certificate of Responsibility = Null and Void Contract

On July 21, 2009, the Mississippi Court of Appeals made it clear that any contract entered into by a party with an unlicensed contractor is null and void. United Plumbing & Heating Company v. AmSouth Bank (Ct. App. No. 2007-CA-01194). This is the first reported decision that addresses the interpretation of Miss. Code Ann. § 31-3-15. This statute provides in pertinent part as follows:

No contract for public or private projects shall be issued or awarded to any contractor who did not have a current certificate of responsibility issued by said board [of contractors] at the time of submission of the bid…Any contract issued or awarded in violation of this section shall be null and void.

In United, the general contractor [United] entered into a contract with an owner [Wee Care] for the construction of a building. The contractor and its subcontractors were not paid for their work. The owner filed bankruptcy and the contractor filed suit against the lender [AmSouth] to recover its contract balance. AmSouth filed a motion for summary judgment arguing that because United did not have a valid certificate of responsibility, the contract was null and void. United argued that it did hold a certificate of responsibility, even though the certificate was issued in a classification different from the type of work being performed for Wee Care. The trial court granted summary judgment in favor of AmSouth. United appealed the decision but the Mississippi Court of Appeals affirmed the trial court’s ruling finding:

[T]he contract entered into between United and Wee Care was null and void because United failed to possess the appropriate certificate of responsibility for the type of work it undertook to perform. Having found that United’s contract with Wee Care was void, it follows that any contractual obligations AmSouth [the lender] may have owed [United or] the subcontractors are also void.

(emphasis added). If a contractor or subcontractor does not have a current certificate of responsibility, it may find itself in the position of having furnished labor and material on a project and not being paid. This could result in a financial disaster for one party and a windfall for the other party.

United makes it abundantly clear that owners, contractors and subcontractors should always check Mississippi State Board of Contractors to determine if the contractor or subcontractor holds a license for the work to be performed. It is also prudent for a party to confirm with the licensed entity that the qualifying party is currently an "owner, or a responsible managing employee, or a responsible managing officer, or a member of the executive staff…" See, Who Can be a "Qualifying Party" for a Contractor’s Certificate of Responsibility? Posted on this blog site by Christopher Solop, May 13, 2009.  (The State Board of Contractors has recently proposed an amendment to Rule L shortening the period to replace a qualifying party after the individual holding the certificate of responsibility leaves the employment of the company from 180 days to 90 days. This change will take effect on October 8, 2009.)

 

When is Enough, Enough - The "Shaken Faith Doctrine"

 

Contractors are occasionally confronted with a subcontractor that just cannot seem to get the job accomplished in a timely or satisfactory manner. Despite repeated warnings, the subcontractor’s performance may not improve. Because termination is an extreme remedy, contractors are generally hesitant to terminate a subcontractor. But when is enough, enough? The Court of Appeals for Mississippi provided some guidance on this issue in Byrd Brothers, LLC v. Herring, 861 So.2d 1070 (Miss. Ct. App. 2003).

In Byrd, the contractor retained a subcontractor to perform plumbing work on a condominium complex. Shortly after the plumbing work commenced there was a dispute concerning the scope of work to be performed by the plumbing subcontractor. There were also issues with the quality of the work performed by the plumbing subcontractor. The contractor repeatedly requested the plumbing subcontractor remedy the deficiencies. However, the plumbing subcontractor failed to adequately address the concerns complaining the contractor was "being too picky". When the contractor discovered billing irregularities, the plumbing subcontractor was asked to leave the project site. The contractor later requested the plumbing subcontractor meet to discuss his performance issues and completion of the project but the plumbing subcontractor refused unless the contractor immediately paid him some money. When this did not occur, the plumbing subcontractor refused to meet and did not to return to the project. The contractor retained another plumbing subcontractor to complete the work.

The original plumbing subcontractor sued the contractor for the subcontract balance and the contractor asserted a counterclaim against the plumbing subcontractor for the cost to complete the plumbing work. The trial court found in favor of the subcontractor. In reversing the trial court judgment and ordering a new trial, the Mississippi Court of Appeals articulated the following legal principle:

A party who has breached or failed to properly perform a contract has a responsibility and a right to cure the breach. The non-breaching party must give him a reasonable opportunity to cure the breach. However, the right to cure is not unlimited.

Where the breach is a material one, the non-breaching party has a right to end the contract, but in doing so he is also obligated to minimize his damages. Likewise, when the conduct of the breaching party has been of such a nature as to cause a loss of confidence or "shaken faith," the offended party is entitled to end the contract, but he remains responsible for mitigating damages.

 

(Citations omitted.)

The Byrd decision highlights the importance of providing a breaching party the opportunity to cure its breach. One warning may not be enough. Contractors need to be vigilant in their efforts to document incomplete and deficient performance and afford adequate opportunities for the subcontractor to "do the right thing". If the subcontractor fails to timely and satisfactorily respond to the contractor’s demands to cure the incomplete and/or deficient work, the cumulative impact of the incomplete and/or deficient work and the lack of responsiveness on the part of the subcontractor may result in a lack of confidence, i.e. "shaken faith", sufficient to entitle the contractor to complete the work and mitigate its damages.

Who Can be a "Qualifying Party" for a Contractor's Certificate of Responsibility?

To perform any public contract of at least $50,000 or private contract of at least $100,000, a contractor must hold a Certificate of Responsibility issued by the Mississippi State Board of Contractors.  It makes no difference whether the "contract" to be performed is a prime contract or subcontract at any tier.  Miss. Code Ann. 31-3-15.

Moverover, Mississippi law does not permit the "borrowing" of certificates of responsibility.  Only a responsible managing officer, employee, or member of the executive staff of the applicant for the certificate can serve as its qualifying party.  The statutes creating the State Board of Contractors, which governs the licensing of contractors, and that Board's regulations implementing those statutes are designed to prevent one person from serving as the qualifying party for entities in which he or she has not personal or managerial stake or responsibility.  To allow otherwise would dilute the requirements which are meant to ensure the integrity, financial capacity, and technical capability of all entities performing construction in Mississippi.

Miss. Code Ann. 31-3-1 defines a "certificate of responsibility" as a "certificate numbered held by a contractor issued by the board under the provisions of this chapter after the payment of the special privilege license tax..."

Miss. Code Ann. 31-3-13(a) defines who can be the "qualifying party" or an applicant of a certificate of responsibility, whether such application is for a new certificate or a renewal certificate.  Specifically, it states:

The board shall take applicants under consideration after having examined him or them and go thoroughly into the records and examinations, prior to granting any certificate of responsiblity.  If the applicant is an individual, examination may be taken by his personal appearance for examination or by the appearance for examination of one or more of his responsible managing employees; and if a co-partnership or corporation or any other combination or organization, by the examination of one or more of the responsible managing officers or memebers of the executive staff of the applicant's firm, according to its own designation.

The intent clearly is that a qualifying party be a responsible managing employee for or officer of the applicant, whether it's a sole proprietorship or corporation.  The true "responsibility" for which the certificate is issued cannot be determined otherwise.  In construing this requirement the State Board of Contractors promulgated the following regulation which, again, leaves no doubt that the "qualifying party" must be intimately involved in the management and/or ownership of the entity claiming him or her as their qualifying party.  Rule L states:

When the qualifying party terminates employement with the Certificate holder, the Mississippi State Board of Contractors must be notified in writing, by the qualifying party and the Certificate holder, within thirty (30) days of the disassociation and another party must qualify within one hundred eighty (180) days or Certificate holder will be subject to suspension or revocation of its Certificate of Responsibility.

(Emphasis added).

Thus, where a purposed "qualifying party" for Company A is neither a managerial employee nor an officer of that company but, in fact, owns or is the officer of another, unrelated Company B, but Company B routinely serves as a subcontractor to Company A, Company A and its purported "qualifying party" are in violation of MIssissippi law and the Rules and Regulations of the State Board of Contractors.  (This is typically done where owners of two companies do not want to commingle business assets, finances, or interests, but they do want to pursue and perform contracts together.)  Company A's Certificate of Responsibility is null and void as a matter of law.

 

Checklist for Mississippi Construction Contractors

If you have ever been the apparent low bidder on a public construction project and had your bid rejected because of an irregularity in the bid documents, you are not alone.  What is even more frustrating, and will make you fighting mad, is when the public agency decides to waive the same irregularity of a competitor when you are the second low bidder.  Perhaps the best way to avoid this situation is to make sure that you have completed your bid in strict accordance with the instructions to bidders.  I know it is difficult to focus on all the particulars when less than an hour before the bid is to be submitted subcontractors and suppliers are sending in prices or changing the ones previously provided.  Here is a simple bid checklist that may help you avoid those last minute mistakes.

  • Read the "Instruction to Bidders" when you obtain a copy of the solicitation to make sure that there are no unusual or different bid requirements. 
    • Pre-Bid Conference
    • Bid Bond
    • Site Visit
    • Listing of Subcontractors
  • Prepare the bid envelope in advance, identifying (1) the project, (2) the person to whom the bid is to be submitted, (3) the location where the bid is to be submitted and (4) the date and time for the submission of the bid.  ALWAYS PLACE CERTIFICATE OF RESPONSIBILITY NUMBER ON THE OUTSIDE OF THE ENVELOPE.
  • Complete the bid form and check to determine whether all the blank spaces for prices are completed with a dollar amount or a "---" or "-0-".
  • Check your addition and multiplication for unit prices and total bid price.
  • Acknowledge all Amendments/Addenda to the solicitation.
  • List subcontractors, if required.
  • Sign and date the bid documents.
  • Check the bid bond, if required, to make sure that it is in the correct amount and proper form.
  • Place bid documents and bid bond, if required, into envelope and submit.

In the event you are determined to be the apparent low bidder, and your bid is not more than ten percent (10%) above the amount of funds allocated for the project, it is likely that you will be awarded the contract.